Nationwide, Wakefield House

1 min read
Aug 30, 2024 11:30:00 AM

Wakefield House is another recent project that we delivered for Nationwide. Working with Imtech, we supplied a 1000kVA generator packaged into a standard 40ft ISO container to achieve 75dbA at 1 metre. The unit is for standby application with paralleling capabilities to support a business critical data building for the UK’s largest Building Society.

The generator enclosure is complete with a 10,000ltr fuel tank, fill point cabinet and equipped with ComAp InteliSys NT controls. The installation provides a standby application supporting 12 independent site loads via break transfer system, furnished with paralleling capability Demand Response participation. The project required a temporary installation of a 450kVA unit, also supplied by APE, to ensure continuous supply were supported to the critical loads during an extensive building development program

Get Email Notifications

No Comments Yet

Let us know what you think